奥克尼群岛首连英国本土:Orkney Link建设提速
作者: 发布时间:2026年09月23日 浏览量:8 字体大小: A+ A-

图片来自网络,版权属于原作者
来源:Offshore Energy 2026-09-23
翻译:国际海事信息网 李姿熠 张运鸿
由SSEN Transmission开发的Orkney Link,将包括在Finstown正在建设的一座新变电站、约14公里穿越奥克尼敷设至Warebeth的地下电缆,以及一条敷设至Caithness的53公里海底电缆,并在那里接入Dounreay的一座新变电站。
未来几个月,27个电缆盘将沿Finstown与靠近Stromness的Warebeth之间的路线各段被调运到位。一旦到位,电缆将使用绞盘设备从每个电缆盘缓慢拉出,穿过已沿全线安装的导管。
安装将分阶段进行,从东部开始,向西推进至Warebeth,在那里电缆将与项目未来的海底段连接。一旦各段电缆安装完成,专业接头团队将把它们熔接在一起,形成一个连续的电缆系统。
此外,Finstown变电站的覆层工程已在夏季完成,首座建筑已完全防风防水。西门子能源因此已开始安装电气设备,电气安装工程将在未来一年持续推进。
“这是Orkney Link项目又一个令人振奋的进展,也是推动这一关键电力基础设施更接近现实的重要里程碑。过去两年,我们的团队和供应链合作伙伴努力工作,建设地下电缆路由,并安装容纳电缆所需的导管,”SSEN Transmission临时项目总监Conor Manning表示。
“看到首批电缆段现已开始安装,是正在取得进展的切实标志。同样令人欣喜的是,Finstown变电站也取得进展,在主建筑结构和覆层完成后,电气安装工程现已启动。这些里程碑共同表明,随着我们更接近首次将奥克尼接入大不列颠电力输电网络,整个项目正在开展大规模活动。”
(本文版权归国际海事信息网所有,图片版权归原作者,转载请注明出处。)
Orkney Link, developed by SSEN Transmission, will comprise a new substation being built at Finstown, approximately 14 kilometers of underground cable installed across Orkney to Warebeth, and a 53-kilometer subsea cable laid to Caithness, where it will connect into a new substation at Dounreay.
Over the coming months, 27 cable drums will be manoeuvred into position along sections of the route between Finstown and Warebeth, near Stromness. Once in position, the cable will be slowly pulled from each drum using winching equipment through ducts that have already been installed along the full route.
The installation will be done in phases, beginning in the east and progressing west towards Warebeth, where the cable will connect with the project’s future subsea section. Once individual cable sections have been installed, specialist jointing teams will fuse them together to create one continuous cable system.
Furthermore, cladding works were completed over the summer months at the Finstown substation, and the first of the buildings is fully wind and watertight. Siemens Energy has thus begun installing the electrical equipment, with electrical installation works to continue throughout the coming year.
“This is another exciting step forward for the Orkney Link project and a major milestone in bringing this critical piece of electricity infrastructure closer to reality. Over the last two years, our teams and supply chain partners have worked hard to construct the underground cable route and install the ducting needed to accommodate the cable,” said Conor Manning, SSEN Transmission’s Interim Project Director.
“Seeing the first sections of cable now being installed is a tangible sign of the progress being made. It’s also fantastic to see the progress being made at Finstown Substation, where electrical installation works are now underway following the completion of the main building structures and cladding. Together, these milestones demonstrate the scale of activity taking place across the project as we move closer to connecting Orkney to the GB electricity transmission network for the first time.”
来源:simic